4 Marla House Construction Cost in Islamabad 2026
Building a 4 Marla house (double storey, 1,620 sq ft covered) in Islamabad costs about Rs 94.15 Lakh — Rs 5,812 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 76.22 Lakh
Rs 4,705 per sq ft
Labour contract: Rs 69.59 Lakh
Standard
Rs 94.15 Lakh
Rs 5,812 per sq ft
Labour contract: Rs 85.96 Lakh
Premium
Rs 1.31 Crore
Rs 8,106 per sq ft
Labour contract: Rs 1.2 Crore
Luxury
Rs 1.89 Crore
Rs 11,691 per sq ft
Labour contract: Rs 1.73 Crore
Only the grey structure? 4 Marla grey structure in Islamabad: Rs 55.71 Lakh
Change anything
Advertisement
How it works
House construction cost in Islamabad
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 41.82 LakhRs 3,439/ft²Complete Rs 71.18 LakhRs 5,854/ft²
- 4 Marla1,620 ft²Grey Rs 55.71 LakhRs 3,439/ft²Complete Rs 94.15 LakhRs 5,812/ft²
- 5 Marla2,026 ft²Grey Rs 69.69 LakhRs 3,440/ft²Complete Rs 1.18 CroreRs 5,832/ft²
- 6 Marla2,296 ft²Grey Rs 78.98 LakhRs 3,440/ft²Complete Rs 1.33 CroreRs 5,781/ft²
- 7 Marla2,678 ft²Grey Rs 92.11 LakhRs 3,440/ft²Complete Rs 1.55 CroreRs 5,770/ft²
- 8 Marla3,060 ft²Grey Rs 1.05 CroreRs 3,440/ft²Complete Rs 1.75 CroreRs 5,723/ft²
- 10 Marla3,376 ft²Grey Rs 1.16 CroreRs 3,440/ft²Complete Rs 1.92 CroreRs 5,694/ft²
- 1 Kanal6,300 ft²Grey Rs 2.17 CroreRs 3,440/ft²Complete Rs 3.52 CroreRs 5,594/ft²
- 2 Kanal11,160 ft²Grey Rs 3.84 CroreRs 3,440/ft²Complete Rs 6.16 CroreRs 5,520/ft²
4 Marla house cost in other cities
Questions people ask
What is the cost of building a 4 Marla house in Islamabad?
About Rs 94.15 Lakh for a double-storey house of 1,620 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 76.22 Lakh and premium about Rs 1.31 Crore.
What is the construction rate per square foot in Islamabad?
About Rs 5,812 per sq ft of covered area at standard quality — Rs 4,705 for economy and Rs 11,691 for luxury.
What does finishing cost for a 4 Marla house in Islamabad?
The grey structure is about Rs 55.71 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 38.43 Lakh.
How much material is needed?
Roughly 437 bags of cement, 2.6 tons of steel, 44 thousand bricks, 2,592 cft of sand and 1,215 cft of crush.