6 Marla Grey Structure Cost in Islamabad 2026
Building the grey structure of a 6 Marla house (double storey, 2,296 sq ft covered) in Islamabad costs about Rs 71.84 Lakh — Rs 3,129 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 64.81 Lakh
Rs 2,823 per sq ft
Labour contract: Rs 58.92 Lakh
Standard
Rs 71.84 Lakh
Rs 3,129 per sq ft
Labour contract: Rs 65.31 Lakh
Premium
Rs 79.61 Lakh
Rs 3,467 per sq ft
Labour contract: Rs 72.38 Lakh
Luxury
Rs 84.77 Lakh
Rs 3,692 per sq ft
Labour contract: Rs 77.06 Lakh
Want it ready to live in? 6 Marla complete house in Islamabad: Rs 1.61 Crore
Make it your own
House construction cost in Islamabad
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 38.04 LakhRs 3,129/ft²Complete Rs 86.24 LakhRs 7,092/ft²
- 4 Marla1,620 ft²Grey Rs 50.68 LakhRs 3,128/ft²Complete Rs 1.12 CroreRs 6,918/ft²
- 5 Marla2,026 ft²Grey Rs 63.39 LakhRs 3,129/ft²Complete Rs 1.43 CroreRs 7,080/ft²
- 6 Marla2,296 ft²Grey Rs 71.84 LakhRs 3,129/ft²Complete Rs 1.61 CroreRs 7,000/ft²
- 7 Marla2,678 ft²Grey Rs 83.79 LakhRs 3,129/ft²Complete Rs 1.85 CroreRs 6,913/ft²
- 8 Marla3,060 ft²Grey Rs 95.74 LakhRs 3,129/ft²Complete Rs 2.11 CroreRs 6,899/ft²
- 10 Marla3,376 ft²Grey Rs 1.06 CroreRs 3,129/ft²Complete Rs 2.31 CroreRs 6,852/ft²
- 1 Kanal6,300 ft²Grey Rs 1.97 CroreRs 3,129/ft²Complete Rs 4.23 CroreRs 6,714/ft²
- 2 Kanal11,160 ft²Grey Rs 3.49 CroreRs 3,129/ft²Complete Rs 7.34 CroreRs 6,575/ft²
6 Marla grey structure cost in other cities
Questions people ask
What is the cost of building the grey structure of a 6 Marla house in Islamabad?
About Rs 71.84 Lakh for a double-storey house of 2,296 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 64.81 Lakh and premium about Rs 79.61 Lakh.
What is the grey structure rate per square foot in Islamabad?
About Rs 3,129 per sq ft of covered area at standard quality — Rs 2,823 for economy and Rs 3,692 for luxury.
What is included in the grey structure?
Digging and foundation, columns, beams and roof slabs, brick walls, plaster, waterproofing and termite proofing, and the water, sewerage, gas and electrical pipes inside the walls — with the labour for all of it.
How much material is needed?
Roughly 620 bags of cement, 3.7 tons of steel, 62 thousand bricks, 3,674 cft of sand and 1,722 cft of crush.