5 Marla House Construction Cost in Islamabad 2026
Building a 5 Marla house (double storey, 2,026 sq ft covered) in Islamabad costs about Rs 1.18 Crore — Rs 5,832 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 95.49 Lakh
Rs 4,713 per sq ft
Labour contract: Rs 87.19 Lakh
Standard
Rs 1.18 Crore
Rs 5,832 per sq ft
Labour contract: Rs 1.08 Crore
Premium
Rs 1.66 Crore
Rs 8,173 per sq ft
Labour contract: Rs 1.51 Crore
Luxury
Rs 2.39 Crore
Rs 11,818 per sq ft
Labour contract: Rs 2.19 Crore
Only the grey structure? 5 Marla grey structure in Islamabad: Rs 69.69 Lakh
Change anything
Advertisement
How it works
House construction cost in Islamabad
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 41.82 LakhRs 3,439/ft²Complete Rs 71.18 LakhRs 5,854/ft²
- 4 Marla1,620 ft²Grey Rs 55.71 LakhRs 3,439/ft²Complete Rs 94.15 LakhRs 5,812/ft²
- 5 Marla2,026 ft²Grey Rs 69.69 LakhRs 3,440/ft²Complete Rs 1.18 CroreRs 5,832/ft²
- 6 Marla2,296 ft²Grey Rs 78.98 LakhRs 3,440/ft²Complete Rs 1.33 CroreRs 5,781/ft²
- 7 Marla2,678 ft²Grey Rs 92.11 LakhRs 3,440/ft²Complete Rs 1.55 CroreRs 5,770/ft²
- 8 Marla3,060 ft²Grey Rs 1.05 CroreRs 3,440/ft²Complete Rs 1.75 CroreRs 5,723/ft²
- 10 Marla3,376 ft²Grey Rs 1.16 CroreRs 3,440/ft²Complete Rs 1.92 CroreRs 5,694/ft²
- 1 Kanal6,300 ft²Grey Rs 2.17 CroreRs 3,440/ft²Complete Rs 3.52 CroreRs 5,594/ft²
- 2 Kanal11,160 ft²Grey Rs 3.84 CroreRs 3,440/ft²Complete Rs 6.16 CroreRs 5,520/ft²
5 Marla house cost in other cities
Questions people ask
What is the cost of building a 5 Marla house in Islamabad?
About Rs 1.18 Crore for a double-storey house of 2,026 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 95.49 Lakh and premium about Rs 1.66 Crore.
What is the construction rate per square foot in Islamabad?
About Rs 5,832 per sq ft of covered area at standard quality — Rs 4,713 for economy and Rs 11,818 for luxury.
What does finishing cost for a 5 Marla house in Islamabad?
The grey structure is about Rs 69.69 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 48.46 Lakh.
How much material is needed?
Roughly 547 bags of cement, 3.2 tons of steel, 55 thousand bricks, 3,242 cft of sand and 1,520 cft of crush.