1 Kanal Grey Structure Cost in Islamabad 2026
Building the grey structure of a 1 Kanal house (double storey, 6,300 sq ft covered) in Islamabad costs about Rs 1.97 Crore — Rs 3,129 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 1.78 Crore
Rs 2,823 per sq ft
Labour contract: Rs 1.62 Crore
Standard
Rs 1.97 Crore
Rs 3,129 per sq ft
Labour contract: Rs 1.79 Crore
Premium
Rs 2.18 Crore
Rs 3,467 per sq ft
Labour contract: Rs 1.99 Crore
Luxury
Rs 2.33 Crore
Rs 3,692 per sq ft
Labour contract: Rs 2.11 Crore
Want it ready to live in? 1 Kanal complete house in Islamabad: Rs 4.23 Crore
Make it your own
House construction cost in Islamabad
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 38.04 LakhRs 3,129/ft²Complete Rs 86.24 LakhRs 7,092/ft²
- 4 Marla1,620 ft²Grey Rs 50.68 LakhRs 3,128/ft²Complete Rs 1.12 CroreRs 6,918/ft²
- 5 Marla2,026 ft²Grey Rs 63.39 LakhRs 3,129/ft²Complete Rs 1.43 CroreRs 7,080/ft²
- 6 Marla2,296 ft²Grey Rs 71.84 LakhRs 3,129/ft²Complete Rs 1.61 CroreRs 7,000/ft²
- 7 Marla2,678 ft²Grey Rs 83.79 LakhRs 3,129/ft²Complete Rs 1.85 CroreRs 6,913/ft²
- 8 Marla3,060 ft²Grey Rs 95.74 LakhRs 3,129/ft²Complete Rs 2.11 CroreRs 6,899/ft²
- 10 Marla3,376 ft²Grey Rs 1.06 CroreRs 3,129/ft²Complete Rs 2.31 CroreRs 6,852/ft²
- 1 Kanal6,300 ft²Grey Rs 1.97 CroreRs 3,129/ft²Complete Rs 4.23 CroreRs 6,714/ft²
- 2 Kanal11,160 ft²Grey Rs 3.49 CroreRs 3,129/ft²Complete Rs 7.34 CroreRs 6,575/ft²
1 Kanal grey structure cost in other cities
Questions people ask
What is the cost of building the grey structure of a 1 Kanal house in Islamabad?
About Rs 1.97 Crore for a double-storey house of 6,300 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 1.78 Crore and premium about Rs 2.18 Crore.
What is the grey structure rate per square foot in Islamabad?
About Rs 3,129 per sq ft of covered area at standard quality — Rs 2,823 for economy and Rs 3,692 for luxury.
What is included in the grey structure?
Digging and foundation, columns, beams and roof slabs, brick walls, plaster, waterproofing and termite proofing, and the water, sewerage, gas and electrical pipes inside the walls — with the labour for all of it.
How much material is needed?
Roughly 1,701 bags of cement, 10.1 tons of steel, 170 thousand bricks, 10,080 cft of sand and 4,725 cft of crush.