4 Marla House Construction Cost in Peshawar 2026
Building a 4 Marla house (double storey, 1,620 sq ft covered) in Peshawar costs about Rs 1.05 Crore — Rs 6,495 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 79.52 Lakh
Rs 4,909 per sq ft
Labour contract: Rs 72.29 Lakh
Standard
Rs 1.05 Crore
Rs 6,495 per sq ft
Labour contract: Rs 95.66 Lakh
Premium
Rs 1.47 Crore
Rs 9,064 per sq ft
Labour contract: Rs 1.33 Crore
Luxury
Rs 2.12 Crore
Rs 13,070 per sq ft
Labour contract: Rs 1.92 Crore
Only the grey structure? 4 Marla grey structure in Peshawar: Rs 48.64 Lakh
Make it your own
House construction cost in Peshawar
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 36.51 LakhRs 3,003/ft²Complete Rs 81.1 LakhRs 6,669/ft²
- 4 Marla1,620 ft²Grey Rs 48.64 LakhRs 3,003/ft²Complete Rs 1.05 CroreRs 6,495/ft²
- 5 Marla2,026 ft²Grey Rs 60.84 LakhRs 3,003/ft²Complete Rs 1.35 CroreRs 6,657/ft²
- 6 Marla2,296 ft²Grey Rs 68.95 LakhRs 3,003/ft²Complete Rs 1.51 CroreRs 6,577/ft²
- 7 Marla2,678 ft²Grey Rs 80.42 LakhRs 3,003/ft²Complete Rs 1.74 CroreRs 6,491/ft²
- 8 Marla3,060 ft²Grey Rs 91.89 LakhRs 3,003/ft²Complete Rs 1.98 CroreRs 6,476/ft²
- 10 Marla3,376 ft²Grey Rs 1.01 CroreRs 3,003/ft²Complete Rs 2.17 CroreRs 6,429/ft²
- 1 Kanal6,300 ft²Grey Rs 1.89 CroreRs 3,003/ft²Complete Rs 3.96 CroreRs 6,291/ft²
- 2 Kanal11,160 ft²Grey Rs 3.35 CroreRs 3,003/ft²Complete Rs 6.87 CroreRs 6,152/ft²
4 Marla house cost in other cities
Questions people ask
What is the cost of building a 4 Marla house in Peshawar?
About Rs 1.05 Crore for a double-storey house of 1,620 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 79.52 Lakh and premium about Rs 1.47 Crore.
What is the construction rate per square foot in Peshawar?
About Rs 6,495 per sq ft of covered area at standard quality — Rs 4,909 for economy and Rs 13,070 for luxury.
What does finishing cost for a 4 Marla house in Peshawar?
The grey structure is about Rs 48.64 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 56.58 Lakh.
How much material is needed?
Roughly 437 bags of cement, 2.6 tons of steel, 44 thousand bricks, 2,592 cft of sand and 1,215 cft of crush.