4 Marla House Construction Cost in Peshawar 2026
Building a 4 Marla house (double storey, 1,620 sq ft covered) in Peshawar costs about Rs 87.52 Lakh — Rs 5,402 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 70.7 Lakh
Rs 4,364 per sq ft
Labour contract: Rs 64.55 Lakh
Standard
Rs 87.52 Lakh
Rs 5,402 per sq ft
Labour contract: Rs 79.91 Lakh
Premium
Rs 1.22 Crore
Rs 7,548 per sq ft
Labour contract: Rs 1.12 Crore
Luxury
Rs 1.77 Crore
Rs 10,902 per sq ft
Labour contract: Rs 1.61 Crore
Only the grey structure? 4 Marla grey structure in Peshawar: Rs 51.97 Lakh
Change anything
Advertisement
How it works
House construction cost in Peshawar
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 39.01 LakhRs 3,208/ft²Complete Rs 66.21 LakhRs 5,445/ft²
- 4 Marla1,620 ft²Grey Rs 51.97 LakhRs 3,208/ft²Complete Rs 87.52 LakhRs 5,402/ft²
- 5 Marla2,026 ft²Grey Rs 65 LakhRs 3,209/ft²Complete Rs 1.1 CroreRs 5,422/ft²
- 6 Marla2,296 ft²Grey Rs 73.67 LakhRs 3,209/ft²Complete Rs 1.23 CroreRs 5,372/ft²
- 7 Marla2,678 ft²Grey Rs 85.92 LakhRs 3,208/ft²Complete Rs 1.44 CroreRs 5,360/ft²
- 8 Marla3,060 ft²Grey Rs 98.17 LakhRs 3,208/ft²Complete Rs 1.63 CroreRs 5,314/ft²
- 10 Marla3,376 ft²Grey Rs 1.08 CroreRs 3,209/ft²Complete Rs 1.78 CroreRs 5,284/ft²
- 1 Kanal6,300 ft²Grey Rs 2.02 CroreRs 3,208/ft²Complete Rs 3.27 CroreRs 5,184/ft²
- 2 Kanal11,160 ft²Grey Rs 3.58 CroreRs 3,208/ft²Complete Rs 5.7 CroreRs 5,110/ft²
4 Marla house cost in other cities
Questions people ask
What is the cost of building a 4 Marla house in Peshawar?
About Rs 87.52 Lakh for a double-storey house of 1,620 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 70.7 Lakh and premium about Rs 1.22 Crore.
What is the construction rate per square foot in Peshawar?
About Rs 5,402 per sq ft of covered area at standard quality — Rs 4,364 for economy and Rs 10,902 for luxury.
What does finishing cost for a 4 Marla house in Peshawar?
The grey structure is about Rs 51.97 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 35.55 Lakh.
How much material is needed?
Roughly 437 bags of cement, 2.6 tons of steel, 44 thousand bricks, 2,592 cft of sand and 1,215 cft of crush.