7 Marla Grey Structure Cost in Peshawar 2026
Building the grey structure of a 7 Marla house (double storey, 2,678 sq ft covered) in Peshawar costs about Rs 85.92 Lakh — Rs 3,208 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 77.44 Lakh
Rs 2,892 per sq ft
Labour contract: Rs 70.71 Lakh
Standard
Rs 85.92 Lakh
Rs 3,208 per sq ft
Labour contract: Rs 78.45 Lakh
Premium
Rs 95.26 Lakh
Rs 3,557 per sq ft
Labour contract: Rs 86.98 Lakh
Luxury
Rs 1.01 Crore
Rs 3,788 per sq ft
Labour contract: Rs 92.62 Lakh
Want it ready to live in? 7 Marla complete house in Peshawar: Rs 1.44 Crore
Change anything
Advertisement
How it works
House construction cost in Peshawar
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 39.01 LakhRs 3,208/ft²Complete Rs 66.21 LakhRs 5,445/ft²
- 4 Marla1,620 ft²Grey Rs 51.97 LakhRs 3,208/ft²Complete Rs 87.52 LakhRs 5,402/ft²
- 5 Marla2,026 ft²Grey Rs 65 LakhRs 3,209/ft²Complete Rs 1.1 CroreRs 5,422/ft²
- 6 Marla2,296 ft²Grey Rs 73.67 LakhRs 3,209/ft²Complete Rs 1.23 CroreRs 5,372/ft²
- 7 Marla2,678 ft²Grey Rs 85.92 LakhRs 3,208/ft²Complete Rs 1.44 CroreRs 5,360/ft²
- 8 Marla3,060 ft²Grey Rs 98.17 LakhRs 3,208/ft²Complete Rs 1.63 CroreRs 5,314/ft²
- 10 Marla3,376 ft²Grey Rs 1.08 CroreRs 3,209/ft²Complete Rs 1.78 CroreRs 5,284/ft²
- 1 Kanal6,300 ft²Grey Rs 2.02 CroreRs 3,208/ft²Complete Rs 3.27 CroreRs 5,184/ft²
- 2 Kanal11,160 ft²Grey Rs 3.58 CroreRs 3,208/ft²Complete Rs 5.7 CroreRs 5,110/ft²
7 Marla grey structure cost in other cities
Questions people ask
What is the cost of building the grey structure of a 7 Marla house in Peshawar?
About Rs 85.92 Lakh for a double-storey house of 2,678 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 77.44 Lakh and premium about Rs 95.26 Lakh.
What is the grey structure rate per square foot in Peshawar?
About Rs 3,208 per sq ft of covered area at standard quality — Rs 2,892 for economy and Rs 3,788 for luxury.
What is included in the grey structure?
Digging and foundation, columns, beams and roof slabs, brick walls, plaster, waterproofing and termite proofing, and the water, sewerage, gas and electrical pipes inside the walls — with the labour for all of it.
How much material is needed?
Roughly 723 bags of cement, 4.3 tons of steel, 72 thousand bricks, 4,285 cft of sand and 2,009 cft of crush.