8 Marla House Construction Cost in Multan 2026
Building a 8 Marla house (double storey, 3,060 sq ft covered) in Multan costs about Rs 1.52 Crore — Rs 4,979 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 1.23 Crore
Rs 4,031 per sq ft
Labour contract: Rs 1.13 Crore
Standard
Rs 1.52 Crore
Rs 4,979 per sq ft
Labour contract: Rs 1.39 Crore
Premium
Rs 2.11 Crore
Rs 6,905 per sq ft
Labour contract: Rs 1.93 Crore
Luxury
Rs 3.02 Crore
Rs 9,871 per sq ft
Labour contract: Rs 2.76 Crore
Only the grey structure? 8 Marla grey structure in Multan: Rs 92.29 Lakh
Change anything
Advertisement
How it works
House construction cost in Multan
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 36.67 LakhRs 3,016/ft²Complete Rs 62.13 LakhRs 5,110/ft²
- 4 Marla1,620 ft²Grey Rs 48.86 LakhRs 3,016/ft²Complete Rs 82.09 LakhRs 5,067/ft²
- 5 Marla2,026 ft²Grey Rs 61.11 LakhRs 3,016/ft²Complete Rs 1.03 CroreRs 5,088/ft²
- 6 Marla2,296 ft²Grey Rs 69.26 LakhRs 3,016/ft²Complete Rs 1.16 CroreRs 5,037/ft²
- 7 Marla2,678 ft²Grey Rs 80.78 LakhRs 3,016/ft²Complete Rs 1.35 CroreRs 5,025/ft²
- 8 Marla3,060 ft²Grey Rs 92.29 LakhRs 3,016/ft²Complete Rs 1.52 CroreRs 4,979/ft²
- 10 Marla3,376 ft²Grey Rs 1.02 CroreRs 3,017/ft²Complete Rs 1.67 CroreRs 4,949/ft²
- 1 Kanal6,300 ft²Grey Rs 1.9 CroreRs 3,016/ft²Complete Rs 3.06 CroreRs 4,850/ft²
- 2 Kanal11,160 ft²Grey Rs 3.37 CroreRs 3,016/ft²Complete Rs 5.33 CroreRs 4,776/ft²
8 Marla house cost in other cities
Questions people ask
What is the cost of building a 8 Marla house in Multan?
About Rs 1.52 Crore for a double-storey house of 3,060 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 1.23 Crore and premium about Rs 2.11 Crore.
What is the construction rate per square foot in Multan?
About Rs 4,979 per sq ft of covered area at standard quality — Rs 4,031 for economy and Rs 9,871 for luxury.
What does finishing cost for a 8 Marla house in Multan?
The grey structure is about Rs 92.29 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 60.07 Lakh.
How much material is needed?
Roughly 826 bags of cement, 4.9 tons of steel, 83 thousand bricks, 4,896 cft of sand and 2,295 cft of crush.