3 Marla House Construction Cost in Multan 2026
Building a 3 Marla house (double storey, 1,216 sq ft covered) in Multan costs about Rs 62.13 Lakh — Rs 5,110 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 49.95 Lakh
Rs 4,108 per sq ft
Labour contract: Rs 45.61 Lakh
Standard
Rs 62.13 Lakh
Rs 5,110 per sq ft
Labour contract: Rs 56.73 Lakh
Premium
Rs 87.59 Lakh
Rs 7,204 per sq ft
Labour contract: Rs 79.98 Lakh
Luxury
Rs 1.27 Crore
Rs 10,477 per sq ft
Labour contract: Rs 1.16 Crore
Only the grey structure? 3 Marla grey structure in Multan: Rs 36.67 Lakh
Change anything
Advertisement
How it works
House construction cost in Multan
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 36.67 LakhRs 3,016/ft²Complete Rs 62.13 LakhRs 5,110/ft²
- 4 Marla1,620 ft²Grey Rs 48.86 LakhRs 3,016/ft²Complete Rs 82.09 LakhRs 5,067/ft²
- 5 Marla2,026 ft²Grey Rs 61.11 LakhRs 3,016/ft²Complete Rs 1.03 CroreRs 5,088/ft²
- 6 Marla2,296 ft²Grey Rs 69.26 LakhRs 3,016/ft²Complete Rs 1.16 CroreRs 5,037/ft²
- 7 Marla2,678 ft²Grey Rs 80.78 LakhRs 3,016/ft²Complete Rs 1.35 CroreRs 5,025/ft²
- 8 Marla3,060 ft²Grey Rs 92.29 LakhRs 3,016/ft²Complete Rs 1.52 CroreRs 4,979/ft²
- 10 Marla3,376 ft²Grey Rs 1.02 CroreRs 3,017/ft²Complete Rs 1.67 CroreRs 4,949/ft²
- 1 Kanal6,300 ft²Grey Rs 1.9 CroreRs 3,016/ft²Complete Rs 3.06 CroreRs 4,850/ft²
- 2 Kanal11,160 ft²Grey Rs 3.37 CroreRs 3,016/ft²Complete Rs 5.33 CroreRs 4,776/ft²
3 Marla house cost in other cities
Questions people ask
What is the cost of building a 3 Marla house in Multan?
About Rs 62.13 Lakh for a double-storey house of 1,216 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 49.95 Lakh and premium about Rs 87.59 Lakh.
What is the construction rate per square foot in Multan?
About Rs 5,110 per sq ft of covered area at standard quality — Rs 4,108 for economy and Rs 10,477 for luxury.
What does finishing cost for a 3 Marla house in Multan?
The grey structure is about Rs 36.67 Lakh; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 25.46 Lakh.
How much material is needed?
Roughly 328 bags of cement, 1.9 tons of steel, 33 thousand bricks, 1,946 cft of sand and 912 cft of crush.