4 Marla Grey Structure Cost in Multan 2026
Building the grey structure of a 4 Marla house (double storey, 1,620 sq ft covered) in Multan costs about Rs 48.86 Lakh — Rs 3,016 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 43.93 Lakh
Rs 2,712 per sq ft
Labour contract: Rs 40.11 Lakh
Standard
Rs 48.86 Lakh
Rs 3,016 per sq ft
Labour contract: Rs 44.61 Lakh
Premium
Rs 54.25 Lakh
Rs 3,349 per sq ft
Labour contract: Rs 49.54 Lakh
Luxury
Rs 57.78 Lakh
Rs 3,567 per sq ft
Labour contract: Rs 52.76 Lakh
Want it ready to live in? 4 Marla complete house in Multan: Rs 82.09 Lakh
Change anything
Advertisement
How it works
House construction cost in Multan
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 36.67 LakhRs 3,016/ft²Complete Rs 62.13 LakhRs 5,110/ft²
- 4 Marla1,620 ft²Grey Rs 48.86 LakhRs 3,016/ft²Complete Rs 82.09 LakhRs 5,067/ft²
- 5 Marla2,026 ft²Grey Rs 61.11 LakhRs 3,016/ft²Complete Rs 1.03 CroreRs 5,088/ft²
- 6 Marla2,296 ft²Grey Rs 69.26 LakhRs 3,016/ft²Complete Rs 1.16 CroreRs 5,037/ft²
- 7 Marla2,678 ft²Grey Rs 80.78 LakhRs 3,016/ft²Complete Rs 1.35 CroreRs 5,025/ft²
- 8 Marla3,060 ft²Grey Rs 92.29 LakhRs 3,016/ft²Complete Rs 1.52 CroreRs 4,979/ft²
- 10 Marla3,376 ft²Grey Rs 1.02 CroreRs 3,017/ft²Complete Rs 1.67 CroreRs 4,949/ft²
- 1 Kanal6,300 ft²Grey Rs 1.9 CroreRs 3,016/ft²Complete Rs 3.06 CroreRs 4,850/ft²
- 2 Kanal11,160 ft²Grey Rs 3.37 CroreRs 3,016/ft²Complete Rs 5.33 CroreRs 4,776/ft²
4 Marla grey structure cost in other cities
Questions people ask
What is the cost of building the grey structure of a 4 Marla house in Multan?
About Rs 48.86 Lakh for a double-storey house of 1,620 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 43.93 Lakh and premium about Rs 54.25 Lakh.
What is the grey structure rate per square foot in Multan?
About Rs 3,016 per sq ft of covered area at standard quality — Rs 2,712 for economy and Rs 3,567 for luxury.
What is included in the grey structure?
Digging and foundation, columns, beams and roof slabs, brick walls, plaster, waterproofing and termite proofing, and the water, sewerage, gas and electrical pipes inside the walls — with the labour for all of it.
How much material is needed?
Roughly 437 bags of cement, 2.6 tons of steel, 44 thousand bricks, 2,592 cft of sand and 1,215 cft of crush.