2 Kanal House Construction Cost in Karachi 2026
Building a 2 Kanal house (double storey, 11,160 sq ft covered) in Karachi costs about Rs 7.1 Crore — Rs 6,364 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 5.48 Crore
Rs 4,907 per sq ft
Labour contract: Rs 4.98 Crore
Standard
Rs 7.1 Crore
Rs 6,364 per sq ft
Labour contract: Rs 6.46 Crore
Premium
Rs 9.6 Crore
Rs 8,601 per sq ft
Labour contract: Rs 8.73 Crore
Luxury
Rs 13.43 Crore
Rs 12,034 per sq ft
Labour contract: Rs 12.21 Crore
Only the grey structure? 2 Kanal grey structure in Karachi: Rs 3.42 Crore
Make it your own
House construction cost in Karachi
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 37.28 LakhRs 3,066/ft²Complete Rs 83.67 LakhRs 6,881/ft²
- 4 Marla1,620 ft²Grey Rs 49.66 LakhRs 3,065/ft²Complete Rs 1.09 CroreRs 6,707/ft²
- 5 Marla2,026 ft²Grey Rs 62.12 LakhRs 3,066/ft²Complete Rs 1.39 CroreRs 6,869/ft²
- 6 Marla2,296 ft²Grey Rs 70.4 LakhRs 3,066/ft²Complete Rs 1.56 CroreRs 6,788/ft²
- 7 Marla2,678 ft²Grey Rs 82.11 LakhRs 3,066/ft²Complete Rs 1.79 CroreRs 6,702/ft²
- 8 Marla3,060 ft²Grey Rs 93.81 LakhRs 3,066/ft²Complete Rs 2.05 CroreRs 6,688/ft²
- 10 Marla3,376 ft²Grey Rs 1.04 CroreRs 3,066/ft²Complete Rs 2.24 CroreRs 6,641/ft²
- 1 Kanal6,300 ft²Grey Rs 1.93 CroreRs 3,066/ft²Complete Rs 4.1 CroreRs 6,502/ft²
- 2 Kanal11,160 ft²Grey Rs 3.42 CroreRs 3,066/ft²Complete Rs 7.1 CroreRs 6,364/ft²
2 Kanal house cost in other cities
Questions people ask
What is the cost of building a 2 Kanal house in Karachi?
About Rs 7.1 Crore for a double-storey house of 11,160 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 5.48 Crore and premium about Rs 9.6 Crore.
What is the construction rate per square foot in Karachi?
About Rs 6,364 per sq ft of covered area at standard quality — Rs 4,907 for economy and Rs 12,034 for luxury.
What does finishing cost for a 2 Kanal house in Karachi?
The grey structure is about Rs 3.42 Crore; finishing — tiles, doors and windows, wiring and fittings, paint, woodwork, bathrooms and kitchens — adds about Rs 3.68 Crore.
How much material is needed?
Roughly 3,013 bags of cement, 17.9 tons of steel, 301 thousand bricks, 17,856 cft of sand and 8,370 cft of crush.