2 Kanal Grey Structure Cost in Rawalpindi 2026
Building the grey structure of a 2 Kanal house (double storey, 11,160 sq ft covered) in Rawalpindi costs about Rs 3.42 Crore — Rs 3,066 per sq ft — at standard quality on today's rates.
Cost by quality
Economy
Rs 3.08 Crore
Rs 2,763 per sq ft
Labour contract: Rs 2.8 Crore
Standard
Rs 3.42 Crore
Rs 3,066 per sq ft
Labour contract: Rs 3.11 Crore
Premium
Rs 3.79 Crore
Rs 3,399 per sq ft
Labour contract: Rs 3.45 Crore
Luxury
Rs 4.04 Crore
Rs 3,619 per sq ft
Labour contract: Rs 3.67 Crore
Want it ready to live in? 2 Kanal complete house in Rawalpindi: Rs 7.1 Crore
Make it your own
House construction cost in Rawalpindi
Double storey, standard quality, on today's rates. Tap a size for its full breakdown.
- 3 Marla1,216 ft²Grey Rs 37.28 LakhRs 3,066/ft²Complete Rs 83.67 LakhRs 6,881/ft²
- 4 Marla1,620 ft²Grey Rs 49.66 LakhRs 3,065/ft²Complete Rs 1.09 CroreRs 6,707/ft²
- 5 Marla2,026 ft²Grey Rs 62.12 LakhRs 3,066/ft²Complete Rs 1.39 CroreRs 6,869/ft²
- 6 Marla2,296 ft²Grey Rs 70.4 LakhRs 3,066/ft²Complete Rs 1.56 CroreRs 6,788/ft²
- 7 Marla2,678 ft²Grey Rs 82.11 LakhRs 3,066/ft²Complete Rs 1.79 CroreRs 6,702/ft²
- 8 Marla3,060 ft²Grey Rs 93.81 LakhRs 3,066/ft²Complete Rs 2.05 CroreRs 6,688/ft²
- 10 Marla3,376 ft²Grey Rs 1.04 CroreRs 3,066/ft²Complete Rs 2.24 CroreRs 6,641/ft²
- 1 Kanal6,300 ft²Grey Rs 1.93 CroreRs 3,066/ft²Complete Rs 4.1 CroreRs 6,502/ft²
- 2 Kanal11,160 ft²Grey Rs 3.42 CroreRs 3,066/ft²Complete Rs 7.1 CroreRs 6,364/ft²
2 Kanal grey structure cost in other cities
Questions people ask
What is the cost of building the grey structure of a 2 Kanal house in Rawalpindi?
About Rs 3.42 Crore for a double-storey house of 11,160 sq ft, at standard quality on a full contract and today's rates. Economy quality comes to about Rs 3.08 Crore and premium about Rs 3.79 Crore.
What is the grey structure rate per square foot in Rawalpindi?
About Rs 3,066 per sq ft of covered area at standard quality — Rs 2,763 for economy and Rs 3,619 for luxury.
What is included in the grey structure?
Digging and foundation, columns, beams and roof slabs, brick walls, plaster, waterproofing and termite proofing, and the water, sewerage, gas and electrical pipes inside the walls — with the labour for all of it.
How much material is needed?
Roughly 3,013 bags of cement, 17.9 tons of steel, 301 thousand bricks, 17,856 cft of sand and 8,370 cft of crush.